  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2028 per the RERA filing.

Promoter

Builder profile

Builder
Mujeeb Abdul Rahiman Patait

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52800051217
Status
New
Stage
Certificate Signed
Possession
April 2028originally December 2027
Construction
67.3% complete
Units sold
0 of 0