High risk
- Possession date passed. The proposed possession date (Feb 2022) has passed with construction at 13.4%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2022 per the RERA filing.
Satellite view of this address
Where it is · 119 2 1
Area guide
What it's like to buy in this area
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
EKVIRA BUILDCON
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100006191
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- February 2022
- Construction
- 13.4% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how the district compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.