High risk
  • Possession date passed. The proposed possession date (Jun 2019) has passed with construction at 36.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2019 per the RERA filing.
Satellite view of this address

Where it is · 76/1, nalegaon

Promoter

Builder profile

Builder
MAHAVIRHOMES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52200016066
Status
New
Stage
Certificate Signed
Possession
June 2019
Construction
36.8% complete
Units sold
0 of 0