High risk
  • Possession delayed ~3 yrs. Originally promised Aug 2023, now proposed Jul 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 90.9%.
Satellite view of this address

Where it is · 33 38, NABARWADA

Area guide

What it's like to buy in NABARWADA

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
LEVEL UP CONSTRUCTIONS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
MORPH DESIGN STUDIO

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52900017742
Status
New
Stage
Certificate Signed
Possession
July 2026originally August 2023
Construction
90.9% complete
Units sold
91 of 144

Keep exploring

Where this project sits, who built it, and how NABARWADA compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.