High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2019, now proposed Jun 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 56.6%.
  • Promised amenities not started. Clubhouse, Landscaped Garden, Kids Play Area are at 0% build with possession due Jun 2024 per the RERA filing.
Satellite view of this address

Where it is · GUT NO 42 GOLWADI WALUJ LINK ROAD, Golwadi Village

Promoter

Builder profile

Builder
Mahesh Vithalrao Labhshetwar

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51500002341
Status
Ongoing
Stage
Certificate Signed
Possession
June 2024originally December 2019
Construction
56.6% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Golwadi Village compares.

Data sourced from the official MahaRERA portal; complaints last synced 18 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.