High risk
  • Behind schedule. Possession is due Apr 2027 but construction is only at 23.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · 1948, Kadegaon

Area guide

What it's like to buy in Kadegaon

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Fortune Enterprises

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P53100051255
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2026
Construction
23.6% complete
Units sold
0 of 155