Fortune Vue A & B Wing
1986 1987, 400011
- Possession delayed ~5 yrs. Originally promised Dec 2021, now proposed May 2027 per the RERA filing.
- Behind schedule. Possession is due May 2027 but construction is only at 42.5%.
Where it is · 1986 1987
Area guide
What it's like to buy in this area
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Racecourse views and some of the city's tallest residences.
- Growth drivers:
- Scarcity, racecourse frontage, South Bombay prestige.
- Who buys here:
- Ultra-HNI trophy purchases.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51900011198
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- May 2027originally December 2021
- Construction
- 42.5% complete
- Units sold
- 49 of 127
Keep exploring
Where this project sits, who built it, and how the district compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.