High risk
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 36.4%.
Satellite view of this address

Where it is · 146/1, RAMANAND NAGAR

Area guide

What it's like to buy in RAMANAND NAGAR

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
GAURI CONSTRUCTIONS BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P49900015806
Status
New
Stage
Certificate Signed
Possession
December 2020
Construction
36.4% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how RAMANAND NAGAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.