High risk
  • Possession date passed. The proposed possession date (Jul 2019) has passed with construction at 59.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2019 per the RERA filing.
Satellite view of this address

Where it is · S.NO.35A/A/1/2 PLOT NO.11, NEAR COURT BUILDING WANLESWADI

Promoter

Builder profile

Builder
G P DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P53100008021
Status
Ongoing
Stage
Certificate Signed
Possession
July 2019
Construction
59.1% complete
Units sold
0 of 0