High risk
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 79.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2024 per the RERA filing.

Promoter

Builder profile

Builder
ANSHUMAN BUILDERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P50300026816
Status
New
Stage
Certificate Signed
Possession
June 2024
Construction
79.1% complete
Units sold
0 of 0