High risk
- 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~5 yrs. Originally promised Jun 2021, now proposed Oct 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.
Satellite view of this address
Where it is · 267, -
Area guide
What it's like to buy in this area
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
G S A CONSTRUCTIONS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51900009097
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2026originally June 2021
- Construction
- 90.9% complete
- Units sold
- 62 of 93
Similar projects in Mumbai City
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
PALOMA
-Poss. August 2023
OHANA COUNTY
-Poss. December 20244 complaints
7 HILLS PLOT E
-Poss. December 2025
7 HILLS PLOT D
-Poss. December 2025
7 HILLS PLOT A
-Poss. December 2025
PRATHAMESH AURA 1
-Poss. March 2026
PRATHAMESH AURA 3
-Poss. March 2026
Terminal Two
-Poss. December 2029
Keep exploring
Where this project sits, who built it, and how - compares.
In -
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.