High risk
  • 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~5 yrs. Originally promised Jun 2021, now proposed Oct 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.
Satellite view of this address

Where it is · 267, -

Area guide

What it's like to buy in this area

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
G S A CONSTRUCTIONS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51900009097
Status
Ongoing
Stage
Certificate Signed
Possession
October 2026originally June 2021
Construction
90.9% complete
Units sold
62 of 93

Similar projects in Mumbai City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how - compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.