High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession date passed. The proposed possession date (Apr 2022) has passed with construction at 90.9%.
Satellite view of this address

Where it is · CTS NO 12, Satara

Promoter

Builder profile

Builder
Mangesh Vitthal Wadekar

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52700009659
Status
Ongoing
Stage
Certificate Signed
Possession
April 2022
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Satara

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Satara compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.