High risk
  • Possession date passed. The proposed possession date (Jun 2018) has passed with construction at 55.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2018 per the RERA filing.
Satellite view of this address

Where it is · SR NO 67 PLOT NO 10,11,12, Gimhavane

Promoter

Builder profile

Builder
OMM INFRASTRUCTURE HOUSING CORPORATION

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52800006468
Status
Ongoing
Stage
Certificate Signed
Possession
June 2018
Construction
55.5% complete
Units sold
0 of 0

Similar projects in Gimhavane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Gimhavane compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.