HORIZON TOWER
125/4/1850, Ward FNorth, 400022
- Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Oct 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 80%.
Where it is · 125/4/1850, Ward FNorth
Area guide
What it's like to buy in Ward FNorth
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Central crossroads reborn via freeway and Metro links.
- Growth drivers:
- Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
- Who buys here:
- BKC-bound professionals and long-time Chembur families.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51900009490
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2020originally December 2018
- Construction
- 80% complete
- Units sold
- 0 of 0
Similar projects in Ward FNorth
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Ward FNorth compares.
In Ward FNorth
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.