Under construction

Hrim Ssky City Phase V

MahaRERA P51500021974High risk

by Ashok Baheti

Gut 69-Par Satara, Beed By Pass, 431007

Official record
Dec 2032
Possession
9.1%
Built
0
Complaints
142
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2025, now proposed Dec 2032 per the RERA filing.
Satellite view of this address

Where it is · Gut 69-Par Satara, Beed By Pass

Area guide

What it's like to buy in Beed By Pass

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Ashok Baheti

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51500021974
Status
New
Stage
Certificate Signed
Possession
December 2032originally December 2025
Construction
9.1% complete
Units sold
7 of 142

Keep exploring

Where this project sits, who built it, and how Beed By Pass compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.