High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 23.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · 1143/b, balaji mill road

Promoter

Builder profile

Builder
VAARUSH DEVELOPERS LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P53100034355
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
23.6% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how balaji mill road compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.