All RERA projects

The Promise Ledger — Bengaluru

Every brochure quotes one possession date. MahaRERA is the only place that also keeps the date the builder originally filed. This page is the gap between the two — recomputed live from official disclosures for every project we track, so each number is checkable against the registration it came from.

No tracked projects match these filters yet — try “All” status or a different city.

How these numbers are made

Source. Official MahaRERA portal disclosures for every project we track, recomputed 31 Oct 2026. Nothing here is our estimate of a project — it is the promoter's own filing, re-read.

"Moved the date". The currently proposed completion date is 3 calendar months or more after the original completion date in the same registration. A shorter gap is filing noise, not a broken promise. Slips are measured in calendar months, so a date pushed by exactly two years reads as exactly two years.

The pace line. The feasibility frontier assumes a site can sustain 2.5% of its total build per month — roughly foundation to finish in 40 months. A project below the line isn't doomed; it is claiming a pace faster than a tower typically holds, and that is worth asking about.

Buyer-years. Each delayed project's slip in years multiplied by the homes it had already sold, summed. It measures waiting created, not compensation owed.

Complaints. Disclosed records, not adjudicated outcomes. A complaint is a buyer filing, not a finding of fault. Recovery warrants are MahaRERA's strongest enforcement action and are counted separately.

Developers. Promoter names are grouped by a fuzzy canonical key (stripping "Pvt Ltd", "Developers", "Realty" and the like), so the same builder filing under slightly different names lands in one row.