The Promise Ledger — Bengaluru
Every brochure quotes one possession date. MahaRERA is the only place that also keeps the date the builder originally filed. This page is the gap between the two — recomputed live from official disclosures for every project we track, so each number is checkable against the registration it came from.
- 65 projects have pushed their possession date by 3 months or more. The typical slip is 1 years; the average is 1.1.
- Those slips add up to 4,876 buyer-years of extra waiting across 6,385 homes that were already sold.
Where each year's promises actually went
Projects grouped by the possession year their builder first filed — only years that have already arrived — and how much of each cohort has since moved the date.
- 202315% moved · avg +0.9 yrs
- 202412% moved · avg +1.5 yrs
- 202518% moved · avg +1 yrs
- 20268% moved · avg +0.9 yrs
When a date moves, how far does it move?
Distribution of the 65 slips on record. The longest single slip here is 4.8 years.
- 3–12 months15
- 1–2 years43
- 2–3 years6
- 3–5 years1
- 5+ years0
Which builders keep the date they filed
Share of each developer's dated projects that never pushed possession, over developers with 5 or more such projects here — a perfect record on two projects isn't a record. A kept date and a low PropPin Score can sit together: the score also carries complaints, warrants, litigation and mortgages, so a builder who hits every deadline can still be answering for everything else.
Best kept-date record
| Developer | Proj. | Kept | Score |
|---|---|---|---|
| SOBHA LIMITED | 27 | 100% | 100 · A+ |
| Brigade Enterprises Ltd | 19 | 100% | 100 · A+ |
| SUMADHURA INFRACON PRIVATE LIMITED | 14 | 100% | 100 · A+ |
| Godrej Properties Limited | 12 | 100% | 100 · A+ |
| DS Max Properties Private Limited | 11 | 100% | 100 · A+ |
| PIONIER PPROJECT | 8 | 100% | 100 · A+ |
| Bhartiya Urban Pvt Ltd | 8 | 100% | 100 · A+ |
| TRIFECTA PROJECTS PRIVATE LIMITED | 7 | 100% | 100 · A+ |
| MANA PROJECTS PVT LTD | 7 | 100% | 100 · A+ |
| Puravankara Limited | 7 | 100% | 100 · A+ |
Most moved dates
| Developer | Proj. | Kept | Score |
|---|---|---|---|
| BREN CORPORATION PRIVATE LIMITED | 7 | 71% | 100 · A+ |
| PRESTIGE ESTATES PROJECTS LTD | 18 | 78% | 100 · A+ |
| SRI BALAJI VENTURES | 5 | 80% | 95 · A+ |
| AFFINITY PROJECTS | 5 | 80% | 100 · A+ |
| CASA GRANDE GARDEN CITY BUILDERS PVT LTD | 13 | 85% | 100 · A+ |
| Sattva Resi Private Limited | 7 | 100% | 100 · A+ |
| GRC INFRA | 6 | 100% | 100 · A+ |
| GOYAL HARIYANA CONSTRUCTIONS | 6 | 100% | 100 · A+ |
| Lodha Developers Limited | 6 | 100% | 100 · A+ |
| Provident White Oaks LLP | 6 | 100% | 100 · A+ |
The longest single slips on record
Originally filed date → the date the same registration quotes today.
- SRI BALAJI GREEN WOODS2024 → 2028 +4.8 yrs
- GARUDA GRAND2025 → 2028 +2.9 yrs
- GRAVITY ARANYA2024 → 2026 +2 yrs
- LIVIUM2024 → 2026 +2 yrs
- Olde Town by LW2025 → 2027 +2 yrs
- ASHISH NARAYANA ROW HOUSE2024 → 2026 +2 yrs
- HEAVIE EDEN2024 → 2026 +2 yrs
- Confident Central Mall2025 → 2026 +1 yrs
- KUTEERA2026 → 2027 +1 yrs
- SGK SAI SONNA KODUM2026 → 2027 +1 yrs
What buyers did about it
Complaints, misc. applications and recovery warrants disclosed per project. 0 projects here have a clean record; 0 disclose pending litigation and 0 are mortgaged to a lender.
How these numbers are made
Source. Official MahaRERA portal disclosures for every project we track, recomputed 31 Oct 2026. Nothing here is our estimate of a project — it is the promoter's own filing, re-read.
"Moved the date". The currently proposed completion date is 3 calendar months or more after the original completion date in the same registration. A shorter gap is filing noise, not a broken promise. Slips are measured in calendar months, so a date pushed by exactly two years reads as exactly two years.
The pace line. The feasibility frontier assumes a site can sustain 2.5% of its total build per month — roughly foundation to finish in 40 months. A project below the line isn't doomed; it is claiming a pace faster than a tower typically holds, and that is worth asking about.
Buyer-years. Each delayed project's slip in years multiplied by the homes it had already sold, summed. It measures waiting created, not compensation owed.
Complaints. Disclosed records, not adjudicated outcomes. A complaint is a buyer filing, not a finding of fault. Recovery warrants are MahaRERA's strongest enforcement action and are counted separately.
Developers. Promoter names are grouped by a fuzzy canonical key (stripping "Pvt Ltd", "Developers", "Realty" and the like), so the same builder filing under slightly different names lands in one row.