Under construction

Kalpataru Azuro

MahaRERA P51900045295High risk

by Kalpataru Properties Pvt. Ltd.

C.S Nos. 3/590, 4/590 of Malabar-Cambala Hill Division, Mumbai City, 400006

Official record
Dec 2027
Possession
54.4%
Built
0
Complaints
14
Units
High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Mortgaged to a lender (₹1750 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹1750 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Area guide

What it's like to buy in Mumbai City

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Kalpataru Properties Pvt. Ltd.

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
M/S Entech Consultant (Form 1 & Form 4)

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51900045295
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
54.4% complete
Units sold
6 of 14

Similar projects in Mumbai City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mumbai City compares.

Data sourced from the official MahaRERA portal; complaints last synced 1 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.