Caution
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 78.2%.

Promoter

Builder profile

Builder
KALPANA PUNDALIK TELMASRE

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P50900016862
Status
New
Stage
Certificate Signed
Possession
December 2019
Construction
78.2% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how BRAHAMPURI compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.