  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2027 per the RERA filing.

Promoter

Builder profile

Builder
N D DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
RAHUL NALAWADE Laxman Nalawade

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52700054039
Status
New
Stage
Certificate Signed
Possession
January 2027originally September 2026
Construction
72.7% complete
Units sold
0 of 26

Similar projects in KOLKI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how KOLKI compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.