Caution
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 90.9%.

Promoter

Builder profile

Builder
Pranav Prakash Kamat

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52900050327
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
90.9% complete
Units sold
18 of 30

Similar projects in Kankavali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kankavali compares.

Data sourced from the official MahaRERA portal; complaints last synced 12 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.