Kandre Residency
25/1 and 2 and 26/2, Isabavi, 413304
- Possession delayed ~2 yrs. Originally promised Jun 2025, now proposed Dec 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Where it is · 25/1 and 2 and 26/2, Isabavi
Area guide
What it's like to buy in Isabavi
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P52600026821
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally June 2025
- Construction
- 66.7% complete
- Units sold
- 21 of 45
Keep exploring
Where this project sits, who built it, and how Isabavi compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.