High risk
  • Possession date passed. The proposed possession date (Jan 2018) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2018 per the RERA filing.
Satellite view of this address

Where it is · 4806, Sangli Miraj Kupwad (M Corp.)

Promoter

Builder profile

Builder
SHASHIKALA RAMCHANDRA SALUNKHE

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P53100003176
Status
Ongoing
Stage
Certificate Signed
Possession
January 2018
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Sangli Miraj Kupwad (M Corp.)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Sangli Miraj Kupwad (M Corp.) compares.

Data sourced from the official MahaRERA portal; complaints last synced 23 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.