High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 23.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2021 per the RERA filing.
Satellite view of this address

Where it is · 60/10, Ward FNorth

Area guide

What it's like to buy in Ward FNorth

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
KESAR CORPORATION

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51900005362
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021
Construction
23.6% complete
Units sold
0 of 0

Similar projects in Ward FNorth

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Ward FNorth compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.