Under construction

Laxmi Keshav Nagar

MahaRERA P52800046838High risk

by Pravin Narayan Lad

S.No. 141 H.No. 19/2/16/A,19/7/16/B,19/8/16/C,19/9,19/5,20,21,56, Kasop, 415612

Official record
May 2027
Possession
31.2%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due May 2027 but construction is only at 31.2%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due May 2027 per the RERA filing.

Area guide

What it's like to buy in Kasop

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Pravin Narayan Lad

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52800046838
Status
New
Stage
Certificate Signed
Possession
May 2027
Construction
31.2% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Kasop compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.