High risk
  • Possession date passed. The proposed possession date (Jul 2024) has passed with construction at 25%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2024 per the RERA filing.
Satellite view of this address

Where it is · GUT NO 145 Tisgaon waluj, Waluj Mahnagar 1

Area guide

What it's like to buy in Waluj Mahnagar 1

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SSD BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51500030314
Status
New
Stage
Certificate Signed
Possession
July 2024
Construction
25% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Waluj Mahnagar 1 compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.