High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Jun 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Satellite view of this address

Where it is · S.NO.53, PLOT NO.1C, -

Promoter

Builder profile

Builder
MIRJE AND ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
SACHIN G KANOJE

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P53100049354
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2024
Construction
70.8% complete
Units sold
4 of 6

Similar projects in Sangli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how - compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.