Under construction

MOHSIN RESIDENCY

MahaRERA P52800056428Caution

by REETAJ BUILDERS & DEVELOPERS

S.No. 384/1/Jha, CTS No - 620/A/1/9, SBI Colony, 415639

Official record
Apr 2027
Possession
47.3%
Built
1
Complaints
0
Units
Caution
  • Behind schedule. Possession is due Apr 2027 but construction is only at 47.3%.

Promoter

Builder profile

Builder
REETAJ BUILDERS & DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52800056428
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2026
Construction
47.3% complete
Units sold
0 of 0

Similar projects in SBI Colony

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how SBI Colony compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.