MONT KIARA
222/10 222A/10, Mumbai City, 400019
- Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 41.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2020 per the RERA filing.
Where it is · 222/10 222A/10, Mumbai City
Area guide
What it's like to buy in Mumbai City
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Old central Bombay — colleges, gardens and society redevelopment.
- Growth drivers:
- Central location, rail junctions, redevelopment of 60s societies.
- Who buys here:
- Central-line families and South Indian community roots.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51900002127
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2020originally March 2019
- Construction
- 41.8% complete
- Units sold
- 0 of 0
Similar projects in Mumbai City
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Mumbai City compares.
In Mumbai City
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.