Caution
  • Possession date passed. The proposed possession date (Mar 2020) has passed with construction at 57.3%.
Satellite view of this address

Where it is · 1-A,1-B,2-A,2-B,3-A,6-B,7-A,7-B,8-A,8-B, Nandgaon peth

Promoter

Builder profile

Builder
NAMAN VENTURES PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P50300003113
Status
Ongoing
Stage
Certificate Signed
Possession
March 2020
Construction
57.3% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Nandgaon peth compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.