High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 80.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Promoter

Builder profile

Builder
Aakar Builders & Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52900028211
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
80.9% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Shriramwadi compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.