High risk
  • Possession date passed. The proposed possession date (May 2019) has passed with construction at 43.2%.
Satellite view of this address

Where it is · 159-2-1-1A-1 Plot No 42-3, Swami Samarath Colony

Promoter

Builder profile

Builder
J.R.P. Constructions

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P53100004210
Status
Ongoing
Stage
Certificate Signed
Possession
May 2019
Construction
43.2% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Swami Samarath Colony compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.