  • Possession date passed. The proposed possession date (Apr 2021) has passed with construction at 90.9%.

Promoter

Builder profile

Builder
Mayuresh Rajvardhan Builders and Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P53000018497
Status
New
Stage
Certificate Signed
Possession
April 2021
Construction
90.9% complete
Units sold
0 of 0