Om Gopal - Floor 3 to 9
by Omkar Realtors and Developers Private Limited
FP No. 569 pt of TPS 4 Mahim Division, Ward GNorth, 400028
- Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
- Possession delayed ~5 yrs. Originally promised Dec 2020, now proposed Jun 2026 per the RERA filing.
- 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 90.9%.
Where it is · FP No. 569 pt of TPS 4 Mahim Division, Ward GNorth
Area guide
What it's like to buy in Ward GNorth
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51900012360
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2026originally December 2020
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Ward GNorth
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Ward GNorth compares.
In Ward GNorth
The developer
Research