Under construction

OM RESIDENCY

MahaRERA P53000055106High risk

by SHIVSHAKTI DEVELOPERS

R.S.NO. 779/3/3, PLOT NO.5 AND NEW C.S.NO. 244/1B/4, B WARD, 416012

Official record
Aug 2026
Possession
90.9%
Built
0
Complaints
10
Units
High risk
  • Mortgaged to a lender (₹1.8 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹1.8 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession date passed. The proposed possession date (Aug 2026) has passed with construction at 90.9%.
Satellite view of this address

Where it is · R.S.NO. 779/3/3, PLOT NO.5 AND NEW C.S.NO. 244/1B/4, B WARD

Area guide

What it's like to buy in B WARD

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SHIVSHAKTI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P53000055106
Status
New
Stage
Certificate Signed
Possession
August 2026originally December 2025
Construction
90.9% complete
Units sold
5 of 10