  • Possession delayed ~1 yr. Originally promised Mar 2026, now proposed Jul 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jul 2027 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO. 30/1/2P, VILLAGE - SAMARVARNI

Promoter

Builder profile

Builder
JMB REALTY

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
HARDIK PANCHAL

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P49600000141
Status
New
Stage
Certificate Signed
Possession
July 2027originally March 2026
Construction
76.6% complete
Units sold
155 of 258