High risk
  • Possession delayed ~7 yrs. Originally promised Jun 2018, now proposed Mar 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 89.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2025 per the RERA filing.
Satellite view of this address

Where it is · 326, Sangvi

Promoter

Builder profile

Builder
PARAS BUILDCON

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52700009186
Status
Ongoing
Stage
Certificate Signed
Possession
March 2025originally June 2018
Construction
89.1% complete
Units sold
0 of 0

Similar projects in Sangvi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.