  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Sept 2026 per the RERA filing.
Satellite view of this address

Where it is · 1895, 1896, Ward GNorth

Area guide

What it's like to buy in Ward GNorth

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Shree Siddhivinayak Developer

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51900029734
Status
New
Stage
Certificate Signed
Possession
September 2026originally December 2024
Construction
72.7% complete
Units sold
28 of 88

Similar projects in Ward GNorth

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Ward GNorth compares.

Data sourced from the official MahaRERA portal; complaints last synced 9 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.