Under construction
PEONY
MahaRERA P52800026882High risk
by DSPC INFRACON PRIVATE LIMITED
S NO 102, H NO.1139 ,PLOT NO.12, KHEDSHI, 415639
Post your property hereOwn or renting out a unit in PEONY? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in KHEDSHI come to you.
Jun 2025
Possession
52.7%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~1 yr. Originally promised Feb 2024, now proposed Jun 2025 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 52.7%.
Promoter
Builder profile
DSPC INFRACON PRIVATE LIMITED
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52800026882
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2025originally February 2024
- Construction
- 52.7% complete
- Units sold
- 0 of 0
Similar projects in KHEDSHI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how KHEDSHI compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.