PLUS ART
by CHINTAMANI CONSTRUCTION COMPANY
2/2676, 1/2676, 5/2676, CS No 197, Ward GSouth, 400013
- Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
- Possession delayed ~7 yrs. Originally promised Dec 2021, now proposed Jun 2028 per the RERA filing.
Where it is · 2/2676, 1/2676, 5/2676, CS No 197, Ward GSouth
Area guide
What it's like to buy in Ward GSouth
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Mill-land skyscraper district — corporate HQs, five-stars and sea-view towers.
- Growth drivers:
- Coastal Road and Sea Link access, premium office stock, Worli sea-face cachet.
- Who buys here:
- CXOs, HNIs and investors chasing trophy addresses.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51900003331
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2028originally December 2021
- Construction
- 38.6% complete
- Units sold
- 64 of 107
Similar projects in Ward GSouth
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Ward GSouth compares.
In Ward GSouth
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.