POLITE CASTELLUM
SRY NO. 03P, GAIKWAD NAGAR, PCMC,DIGHI PUNE-411015, DIGHI, 411015
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- 4 appeals at MahaREAT. 4 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession date passed. The proposed possession date (Jun 2018) has passed with construction at 90.9%.
Where it is · SRY NO. 03P, GAIKWAD NAGAR, PCMC,DIGHI PUNE-411015, DIGHI
Area guide
What it's like to buy in DIGHI
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100003477
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2018
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in DIGHI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how DIGHI compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.