High risk
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 45.5%.
Satellite view of this address

Where it is · 130 P NO 1 8 9 15 16, OPP SANGLIKAR MALA

Promoter

Builder profile

Builder
AMIT DASHRATH JAGDALE

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P53100015019
Status
New
Stage
Certificate Signed
Possession
March 2022
Construction
45.5% complete
Units sold
0 of 0