R M Dhariwal Greens Yavatmal Phase 1
by Dhariwal And Chhoriya Developers LLP
Plot No 1, S No 30/1, 30/2, 30/3, 30/4/2, Yavatmal, 445001
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 67%.
Where it is · Plot No 1, S No 30/1, 30/2, 30/3, 30/4/2, Yavatmal
Area guide
What it's like to buy in Yavatmal
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51000009219
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2021originally December 2019
- Construction
- 67% complete
- Units sold
- 0 of 0
Similar projects in Yavatmal
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Yavatmal compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.