High risk
  • 3 appeals at MahaREAT. 3 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Recovery warrant issued. MahaRERA has issued 1 recovery warrant against this project — the strongest enforcement action on record.
  • Possession delayed ~9 yrs. Originally promised Jun 2019, now proposed Dec 2027 per the RERA filing.
  • 8 RERA complaints. 8 complaint records are disclosed against this project on MahaRERA.
Satellite view of this address

Where it is · 2/12, Ward FNorth

Area guide

What it's like to buy in Ward FNorth

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Parel / Dadar EastPremium

Mill-land towers around Maharashtra's busiest rail junction.

Growth drivers:
Hospital cluster jobs, central location, mill plot launches.
Who buys here:
South-Bombay workers wanting new construction.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
R A ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
SPACE AGE CONSULTANTS

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51900001634
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally June 2019
Construction
75.3% complete
Units sold
174 of 194

Similar projects in Ward FNorth

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Ward FNorth compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.