Under construction

RAKA PARK

MahaRERA P49800009342High risk

by ADINATH INFRASTRUCTURE

SURVEY NO 150/2 PLOT NO 20 WALWADI SHIVAR PIN424005, Walwadi (CT), 424005

Official record
Dec 2020
Possession
65.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Aug 2018, now proposed Dec 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 65.9%.
Satellite view of this address

Where it is · SURVEY NO 150/2 PLOT NO 20 WALWADI SHIVAR PIN424005, Walwadi (CT)

Area guide

What it's like to buy in Walwadi (CT)

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
ADINATH INFRASTRUCTURE

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P49800009342
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020originally August 2018
Construction
65.9% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Walwadi (CT) compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.