Under construction

RAMESHWAR COMPLEX

MahaRERA P52900027238High risk

by Pukar

SURVEY NO 415 A HISSA NO 4/36,37,38,39,46,47,48,49, BEHIND NIKHIL LUNCH HOME, 416613

Official record
Apr 2027
Possession
41.1%
Built
3
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 41.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO 415 A HISSA NO 4/36,37,38,39,46,47,48,49, BEHIND NIKHIL LUNCH HOME

Promoter

Builder profile

Builder
Pukar

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52900027238
Status
New
Stage
Certificate Signed
Possession
April 2027originally June 2024
Construction
41.1% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how BEHIND NIKHIL LUNCH HOME compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.