Under construction
Reverie Phase II
MahaRERA P52100001756High risk
Sr. No. 49/2/2, 411014
Post your property hereOwn or renting out a unit in Reverie Phase II? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in the area come to you.
Nov 2018
Possession
81.8%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Nov 2018) has passed with construction at 81.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2018 per the RERA filing.
Satellite view of this address
Where it is · Sr. No. 49/2/2
Promoter
Builder profile
Espree Landmarks
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100001756
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- November 2018
- Construction
- 81.8% complete
- Units sold
- 0 of 0