High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~2 yrs. Originally promised Sept 2026, now proposed Sept 2028 per the RERA filing.
  • 11 RERA complaints. 11 complaint records are disclosed against this project on MahaRERA.
Satellite view of this address

Where it is · 4PT, 5PT, 6PT, AND 7PT, Ward FNorth

Area guide

What it's like to buy in Ward FNorth

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
RUNWAL DEVELOPERS LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51900005685
Status
Ongoing
Stage
Certificate Signed
Possession
September 2028originally September 2026
Construction
48.6% complete
Units sold
534 of 749

Similar projects in Ward FNorth

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Ward FNorth compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.