High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~4 yrs. Originally promised Dec 2019, now proposed Dec 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 81.8%.
Satellite view of this address

Where it is · 9225-B, Daate Mala

Area guide

What it's like to buy in Daate Mala

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Vision Infra Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P53000000151
Status
Ongoing
Stage
Certificate Signed
Possession
December 2023originally December 2019
Construction
81.8% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Daate Mala compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.